1. STUDY OF RAISE DRIVAGE METHODS.
Raise is an underground opening
driven upward from lower level to upper level or one level to a higher level or
to the surface; a raise may be either vertical or inclined. Raising is a
regular operation in the development of underground metalliferous mines.
(a) COMPARTMENT METHOD
Introduction
Initial excavation made from the
lower level in the direction of the raise for 2 m, and then the raise is
divided into Two or Three compartments.
Application: Vertical or very steep raise, Up to
15-20 m
RAISING WITH 2-COMPARTMENT METHOD:
Raising
with shallow holes is started by cutting out a recess at the bottom level, from
which subsequent operations are performed. Work is done from stage sited
1.8-2.0 m from the face. After firing a round of holes the stage is advanced
towards the face. The working stage rests on two or three stull temporarily set
into holes made in the walls of the raise. It consists of wooden planks laid
over the stulls. Holes are drilled from the stage by means of stopers. After the
drilling is completed the drilling equipment and the tools are removed from the
face and the holes are charged with explosives. Before firing/blasting, the
ladder way of the raise is covered by inclined thick wooden planks which guide
the broken rock away into rock compartment. After blasting, the face is cleared
of smoke and the miners inspect it and dress down loose pieces of rock, while
standing under protection of the stage. Then the timber sets are erected and
the working stage is transferred closer to the face. As the face advances, the
rope ladder connects the upper ladder sollar with the working stage.
Cycle of Operation:
Inspection and dressing down the
loose rocks, timbering, extending the ladder way, construction of working stage
and drilling, removing the working stage, charging, firing/blasting, and
clearing the smoke
RAISING WITH 3-COMPARTMENT METHOD:
This method is same as two compartment method. In
this method initially the area is divided in two. One area is used as ore pass.
The second half area is further divided in two parts. One part is used as
ladder way and other used for conducting the pipe lines and cable. The
drilling-blasting and removal of the blasted material of the raise are carried
in the same way.